Product: IESX
Version: GeoFrame 3.5
Application: DataManager
Search Type: FAQ
Topic:
What is the purpose of the Synchronize function (button) in the Share manager?
Description:
What is the purpose of the Synchronize function (button) in the Share manager?
Solution:
Use the Synchronize function to check for differences between a master
seismic project (source) and a shared project (target) and to resolve
those differences by copying information from the source project to the target
project. The check can be done on a survey basis or by individual 2d lines.
Synchronization would be used with any combination of three events:
- expanding the 3Dsurvey/2Dlines extent in the target project when the source
project's data original extent has been expanded
-check/update differences in the data as a result of Renumber2D/Renumber3D
-check/update differences in the data as a result of 3D survey origin/Edit 2D
Last Modified on: 02-NOV-99