Topic:
What does ??? in the Synchronize dialog box mean?
Description:
Synchronizing an interpretation project to a master project, there is a series of ??? in the Conflicted cross-references window. There is no reference to ??? in the symbol dialog box.
Solution:
A normal output in Conflicted cross-references dialog box is: (2D) 2d_slb:slb4 <= cloudspin_maste - 2d_slb:slb4 [= = !] The output with the question marks is: (2D) 2d_slb:slb4 <= cloudspin_maste - ??? [???] The question marks indicate that the master project is allocated somewhere. To resolve the situation, deallocate the master project before proceeding with the synchronize.
Last Modified on: 02-SEP-99