Topic:
How to copy mistie data back to the seismic project.
Description:
I shared data from two different surveys contained in the master seismic project. In the clone, I then moved those lines into a single survey and ran mistie analysis on the data. How do I copy the mistie data back to the master seismic project?
Solution:
1.) In the clone project, move the lines back to the original surveys: DataManager > 2D seismic > 2D surveys - Select surveys from the '2D surveys' and select the line's to move. - Select the appropriate 'Move-> or Move<-' and 'Dismiss'. 2.) In the seismic project, share the mistie class of data from the clone project to the seismic project: DataManager > Seismic > Share - Select clone project. - Select clone 2d survey and mistie class. - Select 'Share' and 'Dismiss'. 3.) Copy the mistie class in the seismic project to a new class in the clone project: DataManager > Seismic > Copy - Select survey and 2d lines. - Select Input class. - Type in output class name. - Select 'Generate'. 4.) Unshare clone project: DataManager > Seismic > Share - Select survey in 'Remove outgoing references'. - Click 'Unshare'.
Last Modified on: 04-DEC-98